Nscale’s £2bn Loughton data center in Essex has planning permission, Microsoft as anchor tenant and a 90MW grid connection agreement. Reporting picked up by the Guardian on 24 September says UK Power Networks has told the company the grid can’t deliver enough electricity until the early to mid 2030s, so the planned 2027 opening is gone. It’s the clearest UK example yet of power, rather than planning, deciding when a project opens. For anyone pricing UK data center work, program risk now starts at the substation.
Most UK data center headlines this year have been about planning, whether that’s objections, call-ins or packed council hearings. Loughton is a sharp reminder that winning consent only gets you to the next queue.
The government named Nscale’s Essex site in its 2025 AI strategy as the largest UK sovereign AI data center. In July, Nscale learned the power wouldn’t arrive in time to open in 2027. In late September, reporting first carried by the Morning Intelligence newsletter and picked up by the Guardian put a rough date on it, with the local network operator reportedly pointing to the early to mid 2030s.
If you build, supply or fund UK data centers, that shifts where the real schedule risk lives. Here’s what happened, why Nscale has plenty of company, and what Ofgem is trying to do about it.
Nscale has consent, a tenant and 90MW agreed, but no realistic power date this decade. Around 315 data centers are queuing for 73GW of connections against a national peak demand of roughly 45GW. Ofgem has proposed a refundable fee of up to £712,500 per megawatt to clear out speculative schemes, and on-site generation is quietly becoming part of the build.
What actually happened at Loughton
Everything was in place except the electricity
Nscale, the Nvidia-backed AI infrastructure firm, is building a £2bn data center at Loughton with Microsoft signed as anchor tenant. It won planning permission and a 90MW connection agreement. The Guardian likens 90MW to the power use of roughly 315,000 homes.
UK Power Networks wouldn’t discuss a single project, but said many data centers connecting to its network are waiting on works to the wider national transmission network before they can operate. National Grid said it was working with NESO, the system operator, to speed up connections where it could.
Nscale says it remains committed to the project and is looking at generating power on site. Back in July it was reported to be in talks over gas fuel cells as a stopgap. The timing is awkward for the company, too, since it filed IPO papers in September for a listing reported at around £26bn.
Nscale isn’t the only one waiting
A queue bigger than the country’s peak demand
In June, Ofgem said 315 data centers were waiting for National Grid connections, together asking for 73GW. Britain’s entire peak demand is about 45GW.
Ofgem’s own figures show how fast the pile-up happened. Contracted demand offers jumped from 41GW to 125GW between November 2024 and June 2025, with data centers accounting for at least 80GW of the total (Ofgem’s data center figures vary a little depending on the snapshot). The regulator has said it’s concerned that a significant number of those projects may never proceed. That’s a big part of the problem, because speculative applications hold capacity that viable projects can’t touch.
For construction, it means the same scarce capacity is being chased by schemes with wildly different odds of ever reaching site. We saw the same pattern in Barbour ABI’s data, where 162 proposed UK schemes worth £101bn translate into just 21 on site.
Consumers should not bear the risks created by speculative projects.Eleanor Warburton, Director for Energy System Design and Development, Ofgem
Ofgem’s answer is a deposit
Up to £712,500 per megawatt to hold your place
Ofgem’s consultation, launched on 29 July and closed on 16 September, proposes a Data Centre Commitment Fee paid when a large data center accepts a connection offer. It would be refunded at energization and forfeited if the project leaves the queue early. The proposed range is £237,500 to £712,500 per megawatt, which Ofgem puts at roughly 2.5% to 7.5% of average project costs.
To give that some scale, a hypothetical 90MW project would be holding somewhere between about £21.4m and £64.1m against its place in the queue. That’s our arithmetic, and the final rate hasn’t been set. Developers would also need to show progress on finance, commercial maturity and procurement to keep their slot.
That procurement milestone is the bit contractors should circle. If developers need evidence of procurement activity to stay in the queue, expect earlier engagement and earlier commitments on long-lead packages. We unpacked the fee in more depth in Ofgem Wants Up to £712,500 a Megawatt Before You Join the Queue. Ofgem says its wider connection reforms have already pulled around 7.8GW of projects forward by an average of six years, so there’s a real prize if this works.
If the grid won’t come, build the power
On-site generation is moving into the construction scope
Nscale’s fallback is to make its own electricity, and it has company. More than 100 UK projects are weighing gas generation while they wait for the grid, according to industry data reported by TNW.
That changes what actually gets built. Gas engines or fuel cells, fuel supply, emissions controls and the extra permitting that comes with them all land on the project team instead of the utility. Transformers and switchgear were already long-lead headaches, as we found when Microsoft’s 38GW target ran into three-year transformer lead times, and on-site power adds yet more equipment chasing the same constrained supply chain.
What to do if you work on UK data centers
Practical steps for contractors, suppliers and investors
Stay ahead of the UK grid squeeze
The Critical Path tracks the power, policy and pipeline data UK contractors need, every week, without the spin.
Join 3000+ ReadersQuick reference: routes to power
| Route to power | What it adds to the build | Main risk |
|---|---|---|
| Wait for a grid connection | Substation and high-voltage works sized to the connection offer | Energization date sits with the network and can be years out (Loughton: early to mid 2030s) |
| On-site gas generation | Engines, fuel supply, emissions controls, additional permits | Running cost, carbon and local opposition |
| Fuel cells | Fuel cell plant plus fuel supply and storage | Cost and supplier capacity at multi-megawatt scale |
| Hold a queue place under Ofgem’s proposals | Refundable fee of £237,500 to £712,500 per MW, plus progress milestones | Fee forfeited if the project exits the queue early |
FAQ
Nscale has planning permission and a 90MW connection agreement, but UK Power Networks has reportedly told it the grid can’t supply enough electricity until the early to mid 2030s. The network operator says many data centers on its patch are waiting on wider transmission works. The planned 2027 opening will be missed. (Source)
Ofgem said in June that 315 data centers were waiting for National Grid connections, asking for 73GW between them, well above Britain’s roughly 45GW peak demand (Source). Contracted demand offers rose from 41GW to 125GW between November 2024 and June 2025, with data centers making up at least 80GW. (Source)
It’s a proposed fee of £237,500 to £712,500 per megawatt, paid when a large data center accepts a connection offer. It’s refunded at energization and forfeited if the project drops out early. The consultation closed on 16 September 2026, and Ofgem’s final decision is still to come. (Source)
Increasingly, yes. Industry data reported by TNW says more than 100 UK projects are weighing gas generation while they wait for the grid, and Nscale has been reported to be in talks over fuel cells for Loughton. That moves power plant, fuel supply and extra permitting into the construction scope. (Source)
Mostly, it means program risk now depends on power dates as much as planning. Contractors should check connection offers and transmission dependencies before committing resource, price any on-site generation as separate scope, and expect clients to procure long-lead items earlier if Ofgem’s procurement milestones go ahead. (Source)
Related Articles
Ofgem Wants Up to £712,500 a Megawatt Before You Join the Queue
£101bn of UK Data Centres. Twenty-One Are Actually on Site.
Microsoft Needs About 1GW a Quarter Until 2032. Transformer Lead Times Run to Three Years.
Trusted Sources
The Guardian: reporting on the Loughton supercomputer delay (24 September 2026)
Resultsense: Nscale’s Loughton AI data centre faces power wait to 2030s
TNW: Britain’s flagship AI data centre can’t get the power to switch on
Ofgem: Ofgem acts to free up grid capacity by tackling speculative data centre projects