CX Tech Ltd has lodged a £16.5bn application for eight data centers and roughly 1GW on the former Chapelcross nuclear site near Annan. It joins 24 hyperscale proposals in Scotland’s planning system, together worth about 6,000MW, more than one and a half times what the whole country draws at peak. The largest data center operating in Scotland today runs at 12MW. Each scheme gets decided on its own, by its own council, and nothing in the framework ranks them against the grid they would all share. If you bid, build or sell into this pipeline, the sorting job falls to you.
Chapelcross was Scotland’s first commercial nuclear power station, generating from 1959 to 2004 and in decommissioning since. On 30 September, Annan-based CX Tech Ltd (formerly CX Power, the Nuclear Decommissioning Authority’s development partner for the site) lodged a planning permission in principle application with Dumfries and Galloway Council: up to 162,000 square meters of data center floorspace across eight buildings of about 120MW each, up to 40 meters high, built over eight years. The company puts construction headcount at 750, permanent direct jobs at 450, and promises 40 apprenticeships a year.
The objections arrived before the paperwork did. A petition against the scheme is approaching 3,000 signatures. Scottish Greens MSP Laura Moodie calls it one of the most concerning data center applications to date, arguing that at full tilt the campus would consume 7 million MWh a year, more than two million homes’ worth, and says the Scottish Government has committed to no decisions on hyperscale schemes before the end of the year, with national guidance due by December. Campaigners point out they have four weeks to read 166 documents.
Chapelcross is the biggest single application, and the least interesting part of the story. The queue it has joined is now arithmetically bigger than the country it sits in.
The arithmetic nobody in the planning system owns
Twenty-four local decisions are quietly adding up to a national energy commitment
The Scotsman’s count, picked up by Resultsense on 8 September, puts 24 hyperscale proposals in front of Scottish planners. Blackdog near Aberdeen and Auchtertool in Fife are 600MW each. Two Ravenscraig schemes come to 1,050MW, two at Chapelhall add 1,000MW, Hurlford in East Ayrshire is 540MW. Several others, including Hunterston, Dunbar and Cockenzie, have no published capacity, which is why 6,000MW is the floor. Fifteen data centers operate in Scotland today. The biggest is 12MW.
Two things about that list should bother anyone with money at risk in it. The pipeline is concentrated, with North Lanarkshire holding six applications and ten of the 24 coming from a single developer, Apatura. And schemes are already falling away: a 600MW site at Dunoon and a 1,000MW scheme at Irvine are both understood to have dropped out. Nobody announced that. It just happened, the way it will keep happening.
Ministers responded in August by requiring planning authorities to flag any application above 50MW within a week of validation. That gives central government visibility. It gives nobody a mechanism to say which 2,000MW of the 6,000MW the grid can actually carry, or in what order. The national planning framework was last updated in 2022, before ChatGPT existed, so every one of these schemes is being judged by rules written for a world that had never met a 600MW building. We covered what the 50MW line now means for developers last month. Chapelcross is its first gigawatt-scale test.
What Chapelcross is doing differently
A power-first application that still can’t settle the brownfield question
Credit where it’s due: CX Tech has clearly read the objection letters from every other Scottish scheme and tried to answer them in advance. The site sits next to an existing 132kV grid supply point. The developer has identified about 1GW of consented or planned renewables within 5km and roughly 2GW within 20km, says the campus will run only on local and regional renewables without competing with homes for supply, and proposes fossil-free backup used only for testing and exceptional outages.
Water is where UK hyperscale schemes have taken the heaviest fire, so the cooling is closed-loop, non-evaporative air: four houses’ worth of water per building per year, 32 households across the campus. The environmental impact assessment covers transport, noise, air quality, biodiversity, landscape, heritage, water, ground, climate and health. Even the MSP leading the opposition concedes Chapelcross ought to be one of the best places in Scotland to put a data center.
Then again, campaigners say the buildings would sit on agricultural fields north of the decommissioned station rather than on the nuclear footprint, and “brownfield” is the word doing most of the political work in the developer’s case. The Greens’ 7 million MWh figure is about consumption, which no cooling design touches. And this is permission in principle only; later phases need further design, commercial and planning decisions, so the eight-year program starts from whenever consent lands. For what objections do to a timeline in practice, see what 7,000 objections at Larbert looked like.
The timeline test
AWS took a year to get a shed replacement through. Chapelcross is asking for 162,000 square meters
One day after the Chapelcross filing went public, Buckinghamshire Council approved an Amazon Web Services data center at Iver, near Slough. AWS bought the site for £132.5m in 2022, applied in October 2025 and got consent on 1 October 2026 for a single two-storey building of 30,525 square meters replacing 17 industrial units. Twelve months, in a data center hub, on a site the applicant already owned, with traffic and water details still to come.
Chapelcross is more than five times the floorspace, on a contested site, with a government that will decide nothing before January and an MSP calling for rejection. If guidance arrives in December as promised, a determination in 2027 would be fast, and the build is eight years after that. Barbour ABI counts £101bn of UK data center schemes proposed and 21 actually on site. Scotland’s 24 will convert at a lower rate, because they are competing with each other for the same wind. The work that lands first will be enabling and grid work, not halls.
How to sort the 24 if you have to bid on them
Rank by power position and consent risk, not by the gigawatt figure on the press release
The UK data center pipeline, sorted by what will actually get built
Weekly analysis on planning, grid and procurement for the people bidding the work, not the people announcing it.
Join 3000+ Readers| Scheme | Location | Published capacity | Status |
|---|---|---|---|
| CX Technology Campus (Chapelcross) | Annan, Dumfries and Galloway | About 1,000MW across eight buildings | Planning permission in principle lodged 30 Sep 2026 |
| Ravenscraig (two schemes) | North Lanarkshire | 1,050MW combined | In planning |
| Chapelhall (two schemes) | North Lanarkshire | 1,000MW combined | In planning |
| Blackdog | Aberdeen | 600MW | In planning |
| Auchtertool | Fife | 600MW | In planning |
| Hurlford | East Ayrshire | 540MW | In planning |
| Hunterston, Dunbar, Cockenzie, Haspielaw | Various | Not published | In planning |
| Dunoon / Irvine | Argyll / North Ayrshire | 600MW / 1,000MW | Understood to have fallen away |
| AWS Iver (for comparison) | Buckinghamshire, England | 30,525 sqm, capacity not published | Approved 1 Oct 2026, 12 months after filing |
Planning permission in principle for up to 162,000 square meters of data center floorspace across eight buildings of about 120MW each, roughly 1GW in total, plus a training center, on the former Chapelcross nuclear site near Annan. The application sets a planning framework only; later phases need further design, commercial and planning approvals. (Source)
CX Tech says 750 jobs during the eight-year construction program, 450 permanent direct jobs in operation, and 40 apprenticeships a year through an on-site training center. Headline coverage has rounded the operational figure to around 500. (Source)
The design uses closed-loop, non-evaporative air cooling. CX Tech expects each building to use about as much water as four houses a year, or 32 households across the whole campus, with free air cooling used wherever the climate allows. (Source)
MSP Laura Moodie says the campus at full capacity would use 7 million MWh a year, equivalent to more than two million homes, would strain the grid, and would exceed the regional greenhouse gas limit by almost double. She wants the application rejected until a national strategy exists. (Source)
Twenty-four hyperscale proposals totaling about 6,000MW, more than one and a half times Scotland’s peak demand, against 15 operating data centers whose largest runs at 12MW. Ten of the 24 come from one developer, Apatura. Several schemes have no published capacity, so the total is a minimum. (Source)
Buckinghamshire Council approved AWS’s 30,525 square meter, single-building data center at Iver on 1 October 2026, twelve months after the October 2025 application, on a site Amazon bought for £132.5m in 2022. It includes 27 HVO-fueled backup generators and a £600,382 air quality offset. (Source)
Related Articles
Scotland’s 50MW Line Is Now the Number Every Data Centre Developer Has to Build Around
£101bn of UK Data Centres. Twenty-One Are Actually on Site.
What 7,000 Objections at Larbert Tell You About Building Data Centres in the UK
Ofgem Wants Up to £712,500 a Megawatt Before You Join the Queue
FutureScot: Massive £16.5bn datacentre campus planned for former Chapelcross nuclear site
STV News: Plans submitted for ‘world’s largest’ data centre at former Chapelcross nuclear power station
Resultsense (via The Scotsman): Scotland’s 24 hyperscale data centre proposals need 6,000MW
DCD: AWS granted planning permission for data center in Iver, UK