ConstructConnect’s October report puts US data center starts at $98.5bn across 153 projects so far in 2026, with August alone adding $14.4bn. The average project now costs $1.18bn and covers 707,000 square feet; a year ago the comparable figures were $507.4m and 493,000 square feet. Cost went up 2.3 times while floor area grew 43%. That gap is density, electrical scope and long-lead equipment, not general inflation, and it lands on whoever signed a fixed-price contract against last year’s unit rates. Here is what the number is made of, where the money is going geographically, and what to change in the contract before you sign the next one.
Last month we wrote about ConstructConnect’s $818 a square foot figure. The October report, by chief economist Michael Guckes and associate economist Devin Bell, moves every number again. The trimmed average cost per square foot is now $867, the median $541, and individual projects run from under $300 to above $2,200 depending on what is inside the box.
The headline comparison is the one that should make a CFO sit forward. Among projects with known price and floor area, the average 2026 data center costs $1.18bn and covers 707,000 square feet. The 2025 comparables were $507.4m and 493,000 square feet. Run the division and the raw cost per square foot moved from roughly $1,030 to roughly $1,670 (that is our arithmetic on ConstructConnect’s averages, not a figure the report states). Whichever cut you prefer, buildings are repricing faster than they are growing, and they have been doing it all year.
Data centers were 24% of all US nonresidential building starts through August. The largest start of the month was AVAIO Digital’s roughly 300-acre, $6bn campus in Little Rock, Arkansas. Projects like that one are what pull the averages.
What the 2.3x is actually made of
Electrical scope, rack density and equipment that costs 75% more than it did in 2019
ConstructConnect does not attribute the cost escalation, and it is worth being careful about that. What the adjacent data tells you is where to look. Electrical systems account for somewhere between 45% and 70% of a data center’s build cost, which we unpacked in why every electrician you need is building a data center. A building whose cost is mostly switchgear, copper, cooling plant and the people installing it does not track steel and concrete indices. It tracks the equipment market, and the equipment market has gone vertical.
Large power transformers now carry lead times of 30 to 36 months, up from 12 to 18 before the shortage. Power transformer prices are up roughly 75% to 77% since 2019; distribution units 78% to 95%. Siemens Energy’s Grid Technologies backlog hit a record €51bn in August, GE Vernova’s is around $176bn, and Eaton’s Electrical Americas rolling orders are up 41%. Those vendors quote with pricing power because they can.
Then there is density. The gap between a $541 median and an $867 average says the distribution has a long tail of very expensive buildings, most likely AI-grade halls with liquid cooling and far higher power per rack. The $2,200-plus projects are not mistakes. They are a different product that happens to share a square-footage metric with a colocation shed.
Where the money is going
Starts moved inland this year; what’s left to break ground is mostly in the South
Geographically, 2026 starts have moved away from the coasts. The five contiguous states from Wisconsin to Ohio have four states reporting $10bn or more each. The band from Texas to Mississippi is similarly strong, with Texas the upward exception at more than $22bn. Along the eastern seaboard, Georgia through Virginia sit between $5bn and over $20bn. Outside those clusters, only North Dakota, Arizona and Pennsylvania have crossed $2bn.
The near-term pipeline looks different. ConstructConnect is tracking 65 projects worth $26.1bn with start dates before the end of 2026, all still in preconstruction and none guaranteed to break ground. Texas holds more than $11bn of that. South Carolina, Virginia, Georgia and West Virginia each hold $2bn or more. The Midwest, which carried so much of the year’s starts, accounts for just 1.5% of what is left. A month ago the same tracker showed 85 projects and $78.7bn waiting on a start date, which the report reads as planned value getting to site rather than disappearing.
For a contractor, that says two things. The Midwest boom is now in delivery, so the labor squeeze there is at its peak. And the next wave of awards is Southern, concentrated, and already priced by somebody. Power infrastructure is riding alongside: starts are up 119.9% on the same period in 2025, and ConstructConnect forecasts another 30% in 2027.
The contract problem
A 2025-priced fixed-price job on an electrically dense building is a solvency question, not a margin question
Say you tendered a hyperscale package in mid-2025 against a market where the average project cost $507m, with a fixed price, a fluctuations clause written for materials, and a program that assumed switchgear on a 12-month lead. Every assumption in that sentence is now wrong, and the client’s have moved too: more racks per hall, more cooling, a bigger substation compound. Some of the delta lands as variation. Some lands as “that was in scope”. On a typical contractor margin, the arithmetic is not forgiving.
Even so, the contract language has not kept up. Frameworks and MSAs signed into the boom tend to carry escalation clauses built for lumber and rebar, and the equipment that actually drives the number sits outside it. The firms that will be fine are the ones treating the transformer delivery date as the schedule and the equipment quote as the price basis. We saw a version of this coming when we looked at what a three-year transformer queue does to a 38GW plan. It does the same thing to a 200MW campus, just with fewer zeros.
- Rebase the price on equipment quotes, not indices. Ask the switchgear and transformer vendors for a quote with a validity window and build the escalation clause around their terms, not a construction cost index that barely moves.
- Separate the building from the fit-out in the contract. Shell and core can take a fixed price. The electrical and mechanical scope on a dense hall should sit on a cost-plus, target-cost or provisional-sum basis until the design freezes.
- Write the long-lead procurement into the program as a client risk. If the owner is free-issuing transformers, the delivery date belongs to them. If you are procuring, price the 30-to-36-month exposure explicitly.
- Check the density assumption in writing. Cost per square foot and cost per megawatt are diverging. Confirm which one the client budgets on and which one your bid is measured against.
The cost numbers behind the data center boom, before they hit your bid
Weekly analysis on starts, pricing and procurement for the people who sign the tender.
Join 3000+ Readers| Measure | 2025 comparable | 2026 year to date (Oct report) | Change |
|---|---|---|---|
| Data center starts | n/a | $98.5bn, 153 projects (Jan to Aug) | August added $14.4bn across 17 projects |
| Average project cost | $507.4m | $1.18bn | About 2.3x |
| Average project size | 493,000 sq ft | 707,000 sq ft | Up about 43% |
| Cost per sq ft, trimmed average | n/a | $867 | Was $818 in the September report |
| Cost per sq ft, trimmed median | n/a | $541 | Range under $300 to over $2,200 |
| Share of US nonresidential starts | n/a | 24% | Through August |
| Near-term planned pipeline | n/a | 65 projects, $26.1bn before year end | Down from 85 projects, $78.7bn a month earlier |
| Large power transformer lead time | 12 to 18 months (pre-shortage) | 30 to 36 months | Prices up 75% to 77% since 2019 |
$98.5bn across 153 projects from January to August 2026, according to ConstructConnect. August alone added $14.4bn across 17 projects, led by AVAIO Digital’s $6bn campus in Little Rock, Arkansas. Data centers made up 24% of all US nonresidential building starts through August. (Source)
Among projects with known price and floor area, the average 2026 data center costs $1.18bn and covers 707,000 square feet. The comparable 2025 figures were $507.4m and 493,000 square feet. After removing the top and bottom 10% by cost per square foot, the median is $541 and the average $867. (Source)
ConstructConnect does not attribute a cause. Adjacent data points to electrical scope (45% to 70% of a data center’s build cost by IBEW estimates), higher rack density and cooling loads, and long-lead electrical equipment whose prices have risen 75% or more since 2019. Buildings whose cost is mostly equipment and specialist labor do not track general material inflation. (Source)
Starts have moved inland. Four of the five states between Wisconsin and Ohio report $10bn or more each; Texas is above $22bn; the Georgia-to-Virginia seaboard ranges from $5bn to over $20bn. Only North Dakota, Arizona and Pennsylvania have crossed $2bn outside those clusters. (Source)
ConstructConnect is tracking 65 projects worth $26.1bn with start dates before year end, all in preconstruction and not guaranteed to proceed. Texas holds more than $11bn; South Carolina, Virginia, Georgia and West Virginia each hold $2bn or more; the Midwest accounts for just 1.5%. (Source)
Large power transformers run roughly 30 to 36 months, up from 12 to 18 before the shortage, based on a DOE-funded national laboratory analysis published in May 2026 and industry surveys. Generation step-up units average about 144 weeks. Siemens Energy targets a 50% capacity expansion by 2030. (Source)
Yes. Year-to-date power infrastructure starts are 119.9% above the same period in 2025, largely because of the $13bn Catarus Commonwealth LNG project that broke ground in August. ConstructConnect forecasts power infrastructure starts to rise a further 30% in 2027. (Source)
Related Articles
Data Centers Now Cost $818 a Square Foot. That Number Is Not Inflation.
Every Electrician You Need Is Building a Data Center
Microsoft Needs About 1GW a Quarter Until 2032. Transformer Lead Times Run to Three Years.