A £16.5bn, 1 Data Center at Chapelcross. Who Wants to Approve It?
CX Tech has asked Dumfries and Galloway Council for permission to build a 1GW data center campus at the former Chapelcross nuclear site near Annan. It filed about two weeks after the Scottish Parliament backed a motion holding that no decisions on hyperscale data centers should be made until national guidance is ready.
The application is for planning permission in principle: eight data center buildings totaling 162,000 square meters, an on-site substation, and a stated investment of £16.5 billion. DCD reports that the project website has construction running from 2027 to 2035 if permission arrives this year.
Power access is already the hard constraint on UK data center delivery, as we covered in our grid queue analysis and again in our September roundup. Chapelcross adds a planning question on top of the power one, and the council has to answer it first.
Image: CX Tech Ltd
Two timetables that only fit if everything goes early
Parliament approved a motion asking the Scottish Government to report back on national planning guidance by the end of this year and to publish it in full within 12 months, according to DCD. Laura Moodie, the Scottish Greens MSP for South Scotland, says the Scottish Government has stated that no decisions will be reached before the end of the year and that guidance will be in place by December. ITPro reported a different expectation, with guidance probably arriving early next year.
CX Tech’s schedule assumes consent in 2026. The two only line up if the guidance lands early and the council decides straight after it, which is a narrow path for anyone pricing a 2027 mobilization.
What the council now has to weigh
Scottish ministers issued two directions on large data centers in the past two months, and Chapelcross is twenty times the 50 MW threshold both of them use. The council also has to deal with the scale of the campus, organized opposition, and a dispute over what kind of land it sits on.
-
Ministerial notification. Since August 17, councils have had to send ministers any application for a data center above 50MW within seven days of validation, a step that lets ministers consider call-in.
-
Mandatory EIA. A September 16 direction requires an environmental impact assessment for new data centers above 50MW. A CX Tech spokesperson told STV News the application includes one covering energy, noise, traffic, landscape, biodiversity, and water.
-
Energy demand. Laura called the application “one of the most seriously concerning data center applications to date,” and the Greens estimate annual electricity consumption at 7 million MWh, equal to the use of over two million homes.
-
Consultation window. Lewis-Ann Garner of the Say NO to Chapelcross AI Data Centre campaign says residents have four weeks to read 166 documents.
-
Site status. Graeme Anderson, CX Tech’s chief executive, describes Chapelcross as a major brownfield energy site. Lewis-Ann says the proposed land is agricultural fields north of the decommissioned plant, and Laura says a decommissioned brownfield site should be the best place for a data center.
-
Market context. STV reports the campus would be bigger than any operating data center in the world, and DCD notes Scotland has traditionally had a very small data center market.
Where the power comes from
CX Tech cites an adjacent 132 kV Grid Supply Point and says it is exploring direct and private-wire connections to wind, solar, and biomass generation so the site runs exclusively on renewable power. Its spokesperson says the campus is designed to use only locally and regionally generated renewable energy and will not compete with homes and businesses for supply.
For scale on the public grid, Ofgem’s figures show the connection queue rising from 41GW to 125GW between November 2024 and June 2025, with 73GW attributed to data centers, against a Great Britain peak demand of 45GW in 2025. Law firm Vinson & Elkins expects Ofgem’s proposed fee to raise developer interest in private wire and on-site generation, which it says brings its own EPC scope, long-lead procurement, and grid-code compliance demands.
If Chapelcross goes the private wire route, the work includes generation links and cabling alongside the eight buildings. The sources we reviewed put no size or cost on that part.
Tenants, contractors, and labor
CX Tech is seeking planning permission in principle, which settles whether the use is acceptable and leaves detailed design to later applications. The coverage we reviewed names no operator. Graeme describes the campus as a platform for several major AI, cloud, and high-performance computing operators to deploy and expand over time.
Ofgem’s proposed milestones ask data centers that want to keep a grid queue position to show a compute offtaker, long-lead procurement, and a binding customer contract. The milestones cover projects waiting for a grid connection, and CX Tech is exploring private-wire connections to local generation.
CX Tech’s spokesperson puts construction employment at 750 jobs and permanent employment at 450 direct jobs, with a training center taking on 40 apprentices a year over the eight-year build. CITB’s Construction Skills Network says Scottish construction needs an extra 26,100 workers between 2024 and 2028, and Skills Development Scotland counts nearly 14,000 construction apprentices in training nationally.
Hinkley Point C offers one benchmark for regional spend, with EDF reporting about 12,000 people on site at peak, another 8,000 in the supply chain, and £5.3 billion spent with South West suppliers. CX Tech says it will support local contractors. The sources give no local spend target for Chapelcross and do not say how much of the £16.5 billion is construction spend.
KEY TAKEAWAYS
-
The filing seeks planning permission in principle only, with no operator named, so contractor work depends on later approvals and on who signs as a tenant.
-
CX Tech’s 2027 start assumes consent this year, while Parliament ties decisions to national guidance with a 12-month publication window.
-
At 1GW, Chapelcross is twenty times the 50MW threshold that now triggers ministerial notification and a mandatory EIA, so it will be tested under both.
-
The developer is exploring private-wire connections to local renewables, which could add generation and cabling scope.
-
The 750 construction jobs are CX Tech’s number, set against a CITB shortfall of 26,100 Scottish construction workers by 2028.
What to ask CX Tech
Parliament has called for decisions to wait until guidance is published, ministers will see this application within a week of validation, and CX Tech’s own timetable starts in 2027. Contractors and engineers approached for early work on Chapelcross could reasonably ask the developer what it will fund before a decision exists and who carries the cost if the decision comes late.