Buildots Says Crews Deliver 63% of Plan. What Happened in Your Best Four Weeks?
Buildots Says Crews Deliver 63% of Plan. What Happened in Your Best Four Weeks?
The Executive Briefing

BRICKS & BYTES BULLETIN
INTELLIGENCE FOR CONSTRUCTION LEADERS, brought to you by Document Crunch
ANNOUNCEMENT
Groundworks – Edition One | London, 11 Nov 2026

Join us on November 11, 2026, at UCL Here East, London, for Groundworks, a one-day, highly curated summit focused on closing the adoption gap across construction, infrastructure, energy, and mission-critical projects.
THIS WEEK
Buildots Says Crews Deliver 63% of Plan. What Happened in Your Best Four Weeks?
Buildots data shows crews nearly doubling output for four straight weeks on most jobs. Plus: how Aramco restarted a bombed pipeline within days, and what 400 US CEOs told KPMG they fear most.
THE EXECUTIVE BRIEFING
THIS WEEK’S KEY TAKEAWAYS
Key Takeaway 1:
The typical project delivers 63% of its planned weekly output, per Buildots’ new benchmarks. Most projects also contain four straight weeks where crews nearly double their usual rate, which gives schedulers a number to chase.
Key Takeaway 2:
Drones hit Aramco’s biggest pipeline last month, and oil flowed again within days. Zero-hour responders, drone inspection mid-incident and locally held repair materials sit behind a response CEO Amin Nasser calls six times faster than average.
Key Takeaway 3:
KPMG’s 400 US CEOs rank cybercrime as the top risk, with 85% expecting it to affect prosperity. Only 9% call AI agents transformational so far, though 84% still name AI a top investment priority.
“Things do go wrong, they will go wrong. We’re in construction after all.”
7 THINGS WORTH YOUR ATTENTION
ON THE RADAR THIS WEEK
-
RELEASE [AEC], Paris, Tuesday – Tech event on AI, BIM and automation for AEC professionals. (More)
-
IoT Tech Expo Europe, Amsterdam, Monday-Tuesday – Industrial AI, physical AI and digital twins. (More)
-
ACADIA, Detroit, Thursday-Saturday – Computational design, robotics and advanced fabrication conference follows Monday workshops. (More)
-
Education Estates, Manchester, Tuesday-Wednesday – Funding, design and management of schools, colleges and universities. (More)
-
Greenbuild, New York, Tuesday-Friday – Retrofits, material reuse and low-embodied-carbon materials headline Invest for Impact. (More)
-
Procore Groundbreak, Orlando, Wednesday-Thursday – AI advisor Zack Kass on where AI will most affect construction. (More)
-
Scottish Construction Summit, Glasgow, Thursday – Procurement, Building Safety Act liabilities and AI in bidding. (More)
POWERED BY:
|
|
|
FULL EXECUTIVE BRIEFING
Buildots Says Crews Deliver 63% of Plan. What Happened in Your Best Four Weeks?
A typical construction project delivers 63% of the work its schedule planned for each week, according to the first benchmarks report from the Buildots Intelligence Lab, which is fully downloadable. Buildots (our podcast sponsor) told me this week that the report is already the most downloaded the company has published.
AI and computer vision capture what is happening on site through 360 cameras and drones, mapped against each project’s 3D model and schedule, and the Lab’s data is anonymized and aggregated from hundreds of projects across housing, offices, schools, hospitals, and data centers. Many industry statistics come from surveys or from people looking back after a job ends, whereas this set was measured on site, activity by activity, week by week.
A planned rate, finally
The Lab picked 21 of the most common jobs on site and measured how much of each gets finished in a normal working week, in feet of pipe, square feet of wall, or doors hung. Hanging drywall is the same task in a Texas hospital and a London office, so the figures compare across projects.
A schedule holds tasks, dates, dependencies, and float but almost never quantities, so the Lab joined each schedule to the material quantities in the 3D model to produce a planned rate for every week. Our piece on the fragmenting scheduling market covers the gap between office schedules and field execution.
Measured against that planned rate, a typical project delivers 63% of the work its schedule expected each week. The best quarter of projects reaches 79%. Mark Tant, who used to run Wates Construction, says that still means losing a day every week. The bottom quarter manages 51%, roughly half. Mark describes an industry that has settled for a 60% productive environment, and 20 of the 21 jobs measured came in slower than their schedules assume.
The four weeks worth studying
Let’s take the example of a drywall crew that closes up about 10,000 square feet of wall (roughly 1,000 square meters) in a typical week. Look back over the whole job, and the crew’s best four weeks in a row ran at nearly double that rate, and the report found the same shape on nearly every project.
The report shows that these fast weeks happen but cannot explain why. Buildots admits this. Whether the room was ready, whether materials arrived, the weather, and the headcount on site are not in the data yet, and the sample is sizable without being large enough to be definitive.
The practical use finds a place in your own records. If a sub says a faster pace is unrealistic, show them the four weeks when their own crew already worked that fast, then ask the site team what was different. One member of the Buildots team puts it as a question for any scheduler: how many clean weeks can this project actually hand its crews? Find the most productive four weeks on your last project, then repeat the exercise on every job after it to see which conditions you can recreate.
How Aramco restarted a bombed pipeline
Drones hit Aramco’s biggest oil pipeline last month, and a pumping station burned down. Bulldozers began cutting a new line the next morning, and oil was moving again within days, according to a Reuters interview with Amin Nasser, Aramco’s chief executive.
Saudi output fell from more than 10 million barrels a day before the war with Iran began in February to below 7 million for most of the first six months, per the International Energy Agency, and was back to about 8 million in September. A Houthi attack this week hit Aramco’s own headquarters complex and caused extensive damage.
Amin traces the current approach to the 2019 attacks on the Abqaiq processing facility, which temporarily knocked out half of Aramco’s production.
“After Abqaiq in 2019, we came up with the idea of rapid response teams, or what we call zero-hour responders.”
The playbook has five parts:
-
Zero-hour responders, whose job is to be on site within minutes of an incident and start work.
-
Rehearsals for several facilities going down at once, since the planning assumption after 2019 stopped being a single failure.
-
Inspection drones that assess damage while an incident is still unfolding, so a repair plan exists by the time it is safe to go in.
-
About 90% of repair materials made locally or held in a local warehouse, with materials on their way before the work starts.
-
Layers of backup, including strategic storage, spare production capacity, more than one grade of crude, the East-West pipeline, a tanker fleet, and the balance sheet.
Amin says the combined response is more than six times faster than the industry average and that no single element delivers it alone. Customers now treat it as a selling point because they “see that Aramco is able to deliver under different scenarios.”
The claims come from Aramco’s own chief executive, and an oil company has margins and scale far beyond a typical contractor, yet a contingency plan works the same way at either size, as a set of things that happen together when a threat arrives.
With headlines like these arriving more often and AI adding to the cybersecurity risk, I think now is a good time to reread your own contingency plans, since things will go wrong on construction sites. The question I would take from Aramco is whether your plan could also give you an edge with clients.
What KPMG’s CEOs fear most
KPMG published its US CEO Outlook on Wednesday, drawn from 400 chief executives of large American companies. Surveys like this arrive every autumn and tend to disagree with each other, though three findings stood out to me.
Cyber leads the risk list
Ask construction executives what keeps CEOs awake, and you will hear labor, inflation, tariffs, and the Middle East. The survey puts cybercrime first, with 85% of CEOs saying it will affect their company’s prosperity over the next three years. Geopolitics follows at 79%, and inflation at 78%.
Spending is following that ranking, with 48% of CEOs increasing their cybersecurity investment. AI is the reason they give, with 78% citing AI-powered social engineering and 76% citing AI-assisted malware or phishing. Tim Walsh, KPMG’s US chair and CEO, says AI and cybersecurity strategy have become inseparable.
Cutting and hiring at the same time
Some 53% of CEOs plan headcount reductions somewhere in the business, up from 35% a year earlier, and 86% are redesigning roles around people working alongside AI, up from 65%. Hiring for AI skills is planned by 79%, up from 64%, while 89% expect total headcount to rise over three years, with 60% of that group expecting growth below 5%.
Spending ahead of results
84% call AI a top investment priority for the next three years, 65% will put at least a tenth of next year’s capital budget into it, and 68% expect a return within one to three years. Asked whether AI agents, the software that carries out tasks as opposed to answering questions, have been transformational for their organization, only 9% said yes.
Looking beyond construction
The Aramco and KPMG stories come from outside our industry, and we included them because readers told us they like hearing how leaders elsewhere run their businesses. I hope they help you think about where your company stands in that wider landscape and what strategic decisions you should take.
Coming up at Bricks and Bytes
For a closer look at what is happening on site, Groundworks, our construction robotics summit, takes place in London on 11 November, and the speaker schedule is now live. The lineup includes:
-
Chief executives of large Tier 1 contractors
-
Government figures from the Department for Business and Trade
-
Founders of some of the only commercially deployed robotic solutions in construction
-
Subcontractors describing the use cases they see on site
-
Representatives from HS2 and data center clients
-
McKinsey on humanoids
-
Investor and contractor panels
The event is UK-focused with a global reach, and much of the content will be repurposed for people who cannot attend. For background on where the money is going, see our look at autonomy funding.
Back in July, I mentioned a group of industry leaders who would hold roundtables to go deep on the issues leaders face, which matters at a very uncertain time, especially with AI. The Bricks & Bytes Council is now holding its first closed-door virtual roundtable, with C-suite leaders from one of the largest US contractors, an architecture firm, and an engineering firm. The group is expected to grow over the coming months, and I hope to share the key takeaways next week, or the week after.